VDOT News - Northern Virginia

RELEASE:

CONTACT:
IMMEDIATE

Michelle Holland 703-586-0487
[email protected]

NOVA-137666

Jan. 11, 2019



Midday Stoppages Planned on Route 29 and University Boulevard in Gainesville Area Week of Jan. 14th for Blasting Operations at Future Park and Ride Lot

FAIRFAX, Va. – Temporary daytime stoppages are planned daily starting Monday, January 14, through Friday, January 18, between 11 a.m. and noon on University Boulevard between Route 29 and I-66. Additionally, the turn lanes from northbound and southbound Route 29 to University Boulevard will be temporarily closed for up to 15 minutes beginning at 11 a.m.

The stoppages are for blasting of storm water drain trenches at the site of the Gainesville Park and Ride Lot being built near the intersection of Route 29 and University Boulevard. Residents and drivers in the area may hear loud noises and should expect travel delays.

All work is weather dependent and will be rescheduled if inclement conditions occur.

The work is part of the Transform 66 Outside the Beltway Project, which is scheduled to be completed in December 2022. The first part of the Gainesville Park and Ride Lot will open in 2019 with 960 parking spaces to serve carpool, vanpool, and commuter bus travellers. 

VDOT and its private partners provide regular email updates to the public on traffic impacts due to construction activity. The public can sign up for these alerts at Transform66.org.

Follow VDOT Northern Virginia on Twitter at @vadotnova.

###



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Jan. 11, 2019