VDOT News - Northern Virginia

RELEASE:

CONTACT:
IMMEDIATE

Michelle Holland 703-586-0487
[email protected]

NOVA-145676

Aug. 6, 2019



I-66 East at Route 234 Business (Sudley Road) Scheduled to Close During Overnight Hours of Friday, August 9, for Bridge Work
Nighttime lane closures, traffic stoppages on I-66 in Centreville area continue this week

UPDATE (8/9) -- The planned closure and detour on I-66 East on Friday night, August 9, has been updated and will now consist of lane closures and temporary stoppages on I-66 East between Route 234 Business (Sudley Road) and Bull Run Drive. The three right lanes will be closed between 10 p.m. and 6 a.m. Temporary traffic stoppages of up to 30 minutes will occur between midnight and 6 a.m. Two westbound lanes will be closed between 9 p.m. and 6 a.m. Drivers should expect delays and consider taking alternate routes. 

FAIRFAX – Continued work installing bridge beams at Bull Run Drive in Centreville will require an extended closure and detour of I-66 East at Route 234 Business (Sudley Road) Friday night, along with lane closures and stoppages of up to 30 minutes on I-66 other nights this week. Drivers on I-66 in both directions should plan for delays in western Fairfax and eastern Prince William counties during overnight hours. 

On Friday night, August 9, I-66 East will be closed at Route 234 Business (Sudley Road) between midnight and 7 a.m. Eastbound traffic will be detoured to Route 234 Business (Sudley Road) northbound, make a right at the traffic signal onto Route 29 North, then follow signs to I-66 East in Centreville.  

These closures are needed for crews to lift and install beams for the new Bull Run Drive bridge over I-66 that is part of the Transform 66 Outside the Beltway Project.

Details include:

Tuesday, August 6: I-66 between Route 234 Business (Sudley Road) and Compton Road

  • Three left lanes will be closed on I-66 East between 10 p.m. and 5 a.m. for crews to move cranes into position.
  • Three left lanes will be closed on I-66 West between 10 p.m. and 5 a.m. for crews to move cranes into position.

Wednesday, August 7, and Thursday, August 8: I-66 between Route 234 Business (Sudley Road) and Compton Road

  • Three right lanes on I-66 East will be closed between 10 p.m. and 5 a.m.
  • Two left lanes on I-66 West will be closed between 9 p.m. and 5 a.m.
  • Periodic stoppages of up to 30 minutes on I-66 East from Sudley Road to east of Bull Run Drive to lift bridge girders into place between midnight and 4 a.m.

Friday, August 9: I-66 between Route 234 East (Sudley Road) and Compton Road

  • Full closure of I-66 East at Route 234 Business (Sudley Road) from midnight to 7 a.m.
  • Traffic will be detoured to Route 234 Business North, turn right at the traffic signal on to Route 29 North, then follow signs to I-66 East
  • Two left lanes on I-66 West will be closed between 9 p.m. and 5 a.m.

Saturday, August 10: I-66 between Route 234 Business (Sudley Road) and Compton Road

  • Three right lanes on I-66 East will be closed between 10 p.m. and 5 a.m.
  • Two left lanes on I-66 West will be closed between 9 p.m. and 5 a.m.
  • Periodic stoppages of up to 30 minutes on I-66 East from Sudley Road to east of Bull Run Drive to lift bridge girders into place between midnight and 4 a.m.

All work is weather dependent and will be rescheduled if inclement conditions occur.

For additional information about the I-66 Outside the Beltway Project, please visit outside.transform66.org.                       
On Twitter, follow VDOT Northern Virginia at @VaDOTNOVA

 ###



Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.

Page last modified: Aug. 17, 2023