VDOT News - Culpeper
RELEASE: CONTACT: |
IMMEDIATE Lou Hatter (540) 717-2890 [email protected] |
CULP 2021-049 Nov. 19, 2021 |
CONSTRUCTION BEGINS MONDAY ON RT. 240 BRIDGE
Crozet Ave. reduced to one lane controlled with signal during rehabilitation work
CULPEPER — Route 240 (Crozet Avenue) will be reduced to one lane at the bridge over Lickinghole Creek south of Crozet beginning Monday. This will allow rehabilitation of the current substandard structure that carries more than 7,000 vehicles per day.
During the construction work, traffic over the bridge will be controlled by a temporary signal; traffic in the open lane will be separated from the work by temporary barriers. Once the work is complete on one side of the bridge traffic will be shifted to the new lane and the opposite side of the bridge will be reconstructed.
Motorists should drive with extreme care as they travel through the work zone. Workers and equipment will be operating near the travel lane and there is likely to be congestion and delays, especially during morning and afternoon commuting hours, due to the lane closure. The advisory speed limit through the project construction area is 15 miles per hour.
The $1.17 million project will be constructed by Clearwater Construction Inc. of Mercer, Pa. It is scheduled for completion in July 2022. Information about the project is available on the Virginia Department of Transportation’s web site at: Route 240 (Crozet Avenue), Albemarle County.
Current traffic conditions and other real-time travel information can be found on the 511 Virginia website, the free VDOT 511 mobile app or by calling 511 from any phone in Virginia. VDOT updates are also on Facebook and the district’s Twitter account, @VaDOTCulp.
(END)
Tweet
Information in VDOT news releases was accurate at the time the release was published. For the most current information about projects or programs, please visit the project or program Web pages. You may find those by searching by keyword in the search Virginia DOT box above.